DAG Format Reference

Specification for the Implementation DAG (Directed Acyclic Graph) output in design documents.


Overview

The Implementation DAG section provides explicit task dependency information in design.md files. It enables:

  • Parallel execution: Identify tasks that can run simultaneously
  • Dependency tracking: Clear visibility into what blocks what
  • Optimized orchestration: Downstream agents can parallelize work

When DAG Is Included

Condition DAG Section
2+ implementation components Included
Single component Omitted (no parallelization value)
All tasks have linear dependencies Included (documents critical path)

Format Specification

The DAG section appears after the "Implementation Plan" section in design.md:

## Implementation DAG

**Parallel Groups** (tasks with no inter-dependencies):

1. [T1, T2, T3] - Foundation components, no shared state
2. [T4, T5] - Can proceed after group 1, independent of each other
3. [T6] - Integration layer

**Dependencies**:

- T4 -> T1 (T4 depends on T1: API contracts)
- T5 -> T2 (T5 depends on T2: data models)
- T6 -> [T4, T5] (T6 depends on both T4 and T5: integration)

**Critical Path**: T1 -> T4 -> T6

Notation

Parallel Groups

Tasks that can execute simultaneously are grouped in brackets:

1. [T1, T2, T3] - Explanation of why these are parallel
Element Description
[T1, T2, T3] Tasks T1, T2, and T3 can run in parallel
Number prefix Sequential group number (1, 2, 3...)
Comment Explanation of why tasks are independent

Dependencies

Dependencies use arrow notation where the arrow points from dependent to prerequisite:

Notation Meaning
T4 -> T1 T4 depends on T1 (T1 must complete before T4 starts)
T6 -> [T4, T5] T6 depends on both T4 and T5

Reading dependencies: "T4 -> T1" reads as "T4 depends on T1" or "T4 requires T1".

Critical Path

The longest dependency chain through the DAG:

**Critical Path**: T1 -> T4 -> T6

This identifies the sequence of tasks that determines minimum total time.

Task ID Rules

Rule Description
Sequential IDs T1, T2, T3... starting from T1
Design mapping Each T{N} corresponds to an Implementation Plan component
Unique IDs No duplicate task IDs within a DAG
Complete coverage Every task in the Implementation Plan gets an ID

Dependency Types

Hard Dependencies (Require Sequential)

Type Example Result
Data dependency Task B reads data Task A writes B -> A
Interface dependency Task B uses API Task A defines B -> A
Build dependency Task B imports module Task A creates B -> A
Sequential workflow Task B validates Task A output B -> A

Not Hard Dependencies (Can Be Parallel)

These do NOT require sequential ordering:

  • Both tasks use the same library
  • Both tasks modify different parts of the same file
  • Both tasks have similar complexity
  • Both tasks are in the same component category

Examples

Multi-Component Feature

## Implementation DAG

**Parallel Groups** (tasks with no inter-dependencies):

1. [T1, T2, T3] - Schema, API types, and UI components have no shared state
2. [T4, T5] - Controller and service layer, independent after types defined
3. [T6] - Integration tests require all components

**Dependencies**:

- T4 -> T1 (controller uses schema types)
- T5 -> T2 (service implements API contracts)
- T6 -> [T4, T5] (tests require both controller and service)

**Critical Path**: T1 -> T4 -> T6

Linear Dependencies

Even with linear dependencies, the DAG documents the critical path:

## Implementation DAG

**Parallel Groups** (tasks with no inter-dependencies):

1. [T1] - Database migration
2. [T2] - Model layer
3. [T3] - API endpoints

**Dependencies**:

- T2 -> T1 (models require schema)
- T3 -> T2 (endpoints use models)

**Critical Path**: T1 -> T2 -> T3

Maximum Parallelization

Independent modules allow high parallelization:

## Implementation DAG

**Parallel Groups** (tasks with no inter-dependencies):

1. [T1, T2, T3, T4] - Four independent utility modules
2. [T5] - Main module importing all utilities

**Dependencies**:

- T5 -> [T1, T2, T3, T4] (main requires all utilities)

**Critical Path**: T1 -> T5 (or any T{1-4} -> T5)

Downstream Consumption

feature-tasker Agent

The feature-tasker parses the DAG to inform task ordering:

  1. Extracts parallel groups from [T1, T2, ...] patterns
  2. Extracts dependencies from T{N} -> T{M} patterns
  3. Applies topological sort for task order
  4. Preserves parallelizable groups in task categories

Backward Compatibility

If no Implementation DAG section exists, downstream agents use sequential ordering based on the Implementation Plan order.

Validation Rules

Rule Enforcement
No cycles Graph must be acyclic
Complete references All T{N} in dependencies must exist in parallel groups
Valid notation Must use specified bracket and arrow syntax